Highway 16 Milling and Paving

New Brunswick

In April of 2024, MacDonald Paving and Construction, a member of the Miller Group, was awarded the contract to mill and pave New Brunswick roads, all the way up to the Confederation Bridge. The team was able to complete 35% of this project by June 21st as requested by the Province of New Brunswick, to mitigate the impact on tourism. The remainder of the project was completed in August 2024

Some key quantities involved in the project: 

  • 160,000 m² of cold planning 
  • 30,000 tonnes of hot mix paving 
  • 140 m of drainage culverts

Summary

Client

Province of New Brunswick

Sector

Paving

Market

Road Building

Year Completed

2024

Cost

$7.4 million
Highway 16 body image 2
Highway 16 body image 1
Highway 16 body image 3

LET’S WORK TOGETHER

We succeed because we respect our people and invest in their development and well-being.

We’re always on the lookout for smart people with the drive to take on challenges, think about what our customers need in new and innovative ways, and deliver creative solutions.

JOIN OUR TEAM

Lets Work Together with Colas Logo