Summary
Client
Ontario Ministry of Transportation (MTO)
Sector
Civil
Market
Road Building
Year Completed
2024
Cost
$157 million
On July 4, 2024, the project team at the MTO 2022 – 2013 – HWY 401& Leslie project successfully completed the deck pour of the Don River bridge. This significant milestone involved pouring 912 cubic meters of concrete over a span of more than 22 continuous hours, requiring meticulous coordination of numerous resources to ensure a smooth operation.
The successful execution of this complex task reflects the dedication and teamwork of Brennan Paving & Construction Ltd, a member of the Miller Group.