Magnetawan River Bridge Rehabilitation Project

Magnetawan Township

Summary

Client

Ontario Ministry of Transportation (MTO)

Sector

Civil

Market

Road Building

Year Completed

2023

Cost

$6.7 million

The Magnetawan River Bridge Rehabilitation Project consisted of the rehabilitation of a unique concrete arch structure located near the Magnetawan First Nation on Hwy 69. The project was completed through our First Nation partnership Shwe Miikaan-Miller 2020 LP and consisted of repairing deteriorated concrete from the substructure, barrier walls and the replacement of the existing expansion joints and bridge deck waterproofing.

This was a 2‑year contract that posed many unique obstacles such as the arches which we had to construct our suspended scaffolding platform from.