Moncton Airport
Moncton
The Greater Moncton Roméo LeBlanc International Airport (YQM) drives over $665 million of economic activity annually, making it one of the top private-sector economic contributors to New Brunswick’s economy, and an important connection point within the central Maritimes.
MacDonald Paving, a member of The Miller Group, successfully completed two runway rehabilitation projects with YQM on time and on budget.
Summary
Client
Greater Moncton Romeo Leblanc International AirportSector
CivilMarket
Aviation / TransportationYear Completed
2021Cost
$7.38 millionProject highlights
- In 2021, we rehabilitated Runway 11 – 29 between July 11 and September 13th. The project period was complicated by COVID restrictions and very wet weather in the Moncton area, which required frequent schedule adjustments.
- The project consisted of milling 148,170 m² of asphalt, followed by two phases of asphalt work, across one major intersection. The team used the TOPCON MMGPS System to meet the strict project specifications of 5mm -/+ tolerance. This project saw the placement of 18, 340 tonnes of Type B asphalt and 20,630 tonnes of Type D 2asphalt. During phase 1 of the project, we also excavated 63,060 m³ of ground material and placed 33,440 tonnes of crushed stone which was graded with TOP CON MM GPS system to ensure accuracy and adherence to specifications.
- In 2019, we successfully rehabilitated Runway 06 – 24. The original time frame for the project was June 24th to September 5th but following the tender close, a tighter schedule was requested as the work progressed through major intersections. This meant working seven days a week with multiple crews on the project simultaneously, and a complicated schedule of people, equipment and workflows between take-offs and landings.
- The project consisted of milling 140,271 m² of asphalt, followed by 5 phases of asphalt work, across three major intersections. To meet the contract specifications of a 5mm +/- tolerance, we used the TOPCON MMGPS System because of the tight accuracy it offers. The project saw a total placement of 22, 582 tonnes of Type B asphalt (base course asphalt) and 17,333 tonnes of Type D asphalt (seal course asphalt).
LET’S WORK TOGETHER
We succeed because we respect our people and invest in their development and well-being.
We’re always on the lookout for smart people with the drive to take on challenges, think about what our customers need in new and innovative ways, and deliver creative solutions.